.

Sunday, February 24, 2019

Tastee Snax Cookies

Managerial Decision Making Led by prof Ocampo y Vilas Business Report Business Report MacPherson Refrigeration Tastee Snax biscuit corporation By Stefanie By Stefanie Adriaenssens, Astrid de P Astrid de Paep, Soundharya Jayaraman Jayaraman, Evie Tanghe & Yudistira Sa Yudistira Sanggramawi jaya 10th Octob 17th October 2012 Antwerp M Antwerp Management School 1 disconcert of Contents INTRODUCTION . .. 3 1PROBLEM STATEMENT .. 4 2 ASSUMPTIONS & APPROXIMATIONS 4 3 SOLUTION get along . 5 4 RESULTS 5 WHAT-IF outline .. 6 6 general RECOMMENDATIONS . 7 7 APPENDIX 8 7. 1 TABLE 1 ACTIVITIES WITH CRASHED beat AND ADDITIONAL constituteS . 7. 2 TABLE 2 CPM DEADLINE stimulus 46,47 & 48 WEEKS.. 9 7. 3 TABLE 3 CPM DEADLINE OUTPUT 48 WEEKS 10 7. 4 TABLE 4 CPM DEADLINE OUTPUT 47 WEEKS 11 7. 5 TABLE 5 CPM DEADLINE INPUT 46 WEEKS 12 7. 6TABLE 6 RECOMMENDATIONS REGARDING CRASH TIME 13 7. 7 FIGURE 1 mesh OF ACTIVITIES 14 2 Introduction Tastee Snax Cookie Company is a manufacturing business o f baked-goods snacks in the southeastern United States. Due to negative press reports slightly fat consumption and introduction of heavy advertisements of no-fat baked goods by opposite manufacturers, Tastee Snax Cookie Company lost a big sh be of the market place the past year.And thus, the fraternity had to develop and manufacture no-fat cookies soon in swan to secure its sh be in the no-fat baked goods market. The vice president of the company was made to understand by an expert that sarcastic Path methodological summary (CPM), a flip-planning scheduling technique, could be used to introduce new-made products in the market. He put a dynamic aim manager in charge to overlook the coordination efforts of different departments in the organization to ensure that the single assigned tasks were spotless on sequence. In this aspect study, we start by addressing the problem statement of introducing a new no-fat cookie to the market.Secondly the objective is identified. third we discuss the assumptions and approximations that need to be considered before determining the issue approach. retentivity in mind the objective of the case, we then analyzed the results. Fin whollyy we award our pep upations to Tastee Snax Cookie Company. 3 1. Problem Statement The problem we address in this report is to provide an boilers suit project plan for Tastee Snax Cookie Company to help launch their new product soon enough to adopt a share in the no-fat baked goods market. This means certain ecisions pull up stakes have to be made regarding the time taken to address every last(predicate) activitivities while keeping the objective in mind. The objective is to determine the most(prenominal) cost effective method to hang the projects deadline. The project plan discussed below has been generated through the use of a projectplanning scheduling technique, searing Path Methodology, to secure the scientific approach. The program schedule provides a numeric basis to beget managerial decisions to shorten the implementation time of the overall project. 2. Assumptions and ApproximationsThe mathematical model created to schedule all the projects is based upon a enactment of simplifying assumptions and approximations. These need to be taken into account in order to make an independent judgment about the models usefulness. The assumptions and approximations of this model are ? The product introduction program has been broken down into three groups of activities question & shootment, Marketing & Advertising, and Promotion ? The description of to each one activity and the indicated time involve for its completion in weeks was taken at face value from the case The tasks to be performed by each department and the estimated durations and deadlines were also considered as disposed ? The preceding activities for each activity are considered as such ? The tasks that could potentially be falled by increase resources were decisions based on the inform ation visible(prenominal) in the case. 4 3. Solution Approach The problem has been modeled into Critical Path Methodology (CPM). The CPM approach is based on a intercommunicate representation that reflects activity precedence relations.As shown in insert 1, the nodes designate activities and their time duration, and the arcs define the precedence relations between the activities. The soonest approach (ES) and Earliest hold back time (EF) for each activity is reckond as shown below. ES = Maximum EF of all its immediate predecessors EF = ES + (Activity completion time) ES and EF are be on the CPM net profit by a pair of minutes, in black, above the node representing the activity. Subsequently, the in style(p) start time (LS) and Latest finish time (LF) was determined for each activity which allows the project to be completed by its minimal completion date.LS and LF was calculated as shown below. LS and LF are represented as a pair of numbers, in red, in CPM network. LF = Mi nimum LS of all immediate successor activities LS = LF (Activity Completion fourth dimension) Based on the information available in the case on slack time in weeks for each activity, the critical path of the model was deduced. A critical path has activities with slide fastener slack and is the longest path in the network. A delay in one of the activities of the critical path results in a delay of the overall project. As give the gate be seen in figure 1, the earliest and in vogue(p) multiplication are the same in the activities of the critical path. 4. ResultsBased on the CPM network drawn we have deduced the following for each activity Earliest Start (ES), Earliest Finish era (EF), Latest Start time (LS) and Latest Finish time (LF) (see Figure 1). The maximum of EF times, 52 weeks, is the estimated completion of the full project. By taking into consideration the slack times in weeks provided in the case, we then arrived at the critical path. The critical path contained the critical activities with goose egg slack time. Critical Path B1-A2-B5-B6-A4-A5-B9-B11-A6-A7-A8 5 5. What-if Analyses The following paragraph discusses supernumerary economical and operational information as provided in the case.The earlier a product would enter the market the quicker it would be able to realize market share. This motivated the Project Manager to develop a inclining of tasks that could be potentially crashed by increasing resources allocated to them (see dishearten 1). In flurry 1, you will find this list of activities that could be performed faster by increasing the cost of operations. According to the crashing analysis, the cheapest way to shorten the project duration by four weeks is to crash three activities. As seen in Table 3 activity A4 should be crashed three weeks and activities B2 and B5 one week.The additional cost to quash the project duration from 52 weeks to 48 weeks is $7,200. The cheapest way to shorten the project duration by five weeks is to crash four activities. As seen in Table 4 activity A4 should be crashed three weeks and activities A7, B2 and B5 one week. The step-down of the project duration by five weeks costs an additional $ 10,700. The CPM analysis shows that the cheapest way to shorten the project duration by six weeks is to crash four activities. As seen in Table 5, activity A4 should be crashed by three weeks, activity A7 by two weeks and activities B2 and B5 by 1 week.To get over the project duration by six weeks, the additional cost adds up to $ 14,200. 6 6. Overall Recommendations The objective of the model was to find a solution to shorten the implementation. That is, to determine the most cost effective way to decrease the projects timeline, which would help Tastee Snax Cookie Company to launch their new product and thereby capturing a market share in the no fat baked foods market. Based on our results, we would state that the maximum number of weeks by which the project can be shortened is 6 weeks. To calculate this, the activities A4, A7, B2 and B5 are crashed resulting the Earliest Finish time (EF) of 46 weeks for the project (See Table 6). Activities A4, A7 and B5 are crashed to their maximum crashed time. The additional cost for crashing the project to 46 weeks can be determined with solver, as already explained in the report, which is $14,200. Hence we recommend that the optimal solution would be to reduce the project duration by 6 weeks at an additional cost of $14,200. 7 7. Appendix 7. 1 Table 1 activities with crashed time and additional cost Activity Develop special Crashed snip Additional Cost Weeks) A3 Original Time (Weeks) ($) 5 3 2200 6 3 3900 6 4 7000 10 8 3200 4 3 1700 4 3 3000 equipment list A4 Prepare manufacturing specifications A7 have and install equipment B2 Develop and test packaging and product names B5 coif taste test B6 Review results and choose products 8 7. 2 Table 2 CPM Deadline Input 46, 47 & 48 weeks 46/47 48 advise DEADLINE = IMMEDIATE PREDEC ESSORS body process A1 A2 A3 A4 A5 A6 A7 A8 B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 B11 B12 C1 C2 C3 C4 C5 NODE natural TIME A B C D E F G H I J K L M N O P Q R S T U V W X Y 2 5 5 6 4 1 6 6 3 10 10 3 4 4 7 4 8 4 5 8 5 4 1 5 6 conventionality hail CRASHTIME 2 5 3 3 4 1 4 6 3 8 10 3 3 3 7 4 8 4 5 8 5 4 1 5 6 CRASH COST 2200 3900 7000 3200 1700 3000 NODE PREDECESS OR B B C D D E F F G H J K L M M N P P P Q Q Q R S T T U V A I B C N D D S F G I J I B L M O X Y E K P Q Q R S I U W X X Y Y U J W J V 9 7. 3 Table 3 CPM Deadline rig 48 weeks CRASHING ANALYSIS 7200 TOTAL PROJECT COST 48 tip TIME ACTIVITY A1 A2 A3 A4 A5 A6 A7 A8 B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 B11 B12 C1 C2 C3 C4 C5 PROJECT NORMAL COST 0 PROJECT CRASH COST 21000 NODE Completion Time Start Time Finish Time Amount Crashed Cost of Crashing Total Cost A B C D E F G H I J K L M N O P Q R S T U V WX Y 2 5 5 3 4 1 6 6 3 9 10 3 3 4 7 4 8 4 5 8 5 4 1 5 6 1 3 10 15 18 35 36 42 0 3 12 5 8 11 11 18 22 31 30 35 3 8 12 13 12 3 8 15 18 22 36 4 2 48 3 12 22 8 11 15 18 22 30 35 35 43 8 12 13 18 18 0 0 0 3 0 0 0 0 0 1 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3900 0 0 0 0 0 1600 0 0 1700 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3900 0 0 0 0 0 1600 0 0 1700 0 0 0 0 0 0 0 0 0 0 0 0 10 7. 4 Table 4 CPM Deadline widening 47 weeks CRASHING ANALYSIS 10700 TOTAL PROJECT COST 47 COMPLETION TIME ACTIVITY A1 A2 A3 A4 A5 A6 A7 A8 B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 B11 B12 C1 C2 C3 C4 C5 PROJECT NORMAL COST 0 PROJECT CRASH COST 21000 NODE CompletionTime Start Time Finish Time Amount Crashed Cost of Crashing Total Cost A B C D E F G H I J K L M N O P Q R S T U V W X Y 2 5 5 3 4 1 5 6 3 9 10 3 3 4 7 4 8 4 5 8 5 4 1 5 6 1 3 10 15 18 35 36 41 0 3 12 5 8 11 11 18 22 31 30 35 3 8 12 13 12 3 8 15 18 22 36 41 47 3 12 22 8 11 15 18 22 30 35 35 43 8 12 13 18 18 0 0 0 3 0 0 1 0 0 1 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3900 0 0 3500 0 0 1600 0 0 1700 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3900 0 0 3500 0 0 1600 0 0 1700 0 0 0 0 0 0 0 0 0 0 0 0 11 7. 5 Table 5 CPM Deadline Outpu t 46 weeks CRASHING ANALYSIS 14200 TOTAL PROJECT COST COMPLETION TIME ACTIVITY A1 A2 A3 A4 A5 A6A7 A8 B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 B11 B12 C1 C2 C3 C4 C5 A B C D E F G H I J K L M N O P Q R S T U V W X Y 21000 Start Time Finish Time Amount Crashed Cost of Crashing Total Cost 1 3 10 15 18 35 36 40 0 3 12 5 8 11 11 18 22 31 30 35 3 8 12 13 12 3 8 15 18 22 36 40 46 3 12 22 8 11 15 18 22 30 35 35 43 8 12 13 18 18 0 0 0 3 0 0 2 0 0 1 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3900 0 0 7000 0 0 1600 0 0 1700 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3900 0 0 7000 0 0 1600 0 0 1700 0 0 0 0 0 0 0 0 0 0 0 0 46 NODE Completion Time 2 5 5 3 4 1 4 6 3 9 10 3 3 4 7 4 8 4 5 8 5 4 1 5 6 0 PROJECT NORMAL COST PROJECT CRASH COST 12 7. Table 6 Recommendations regarding crash time Activity Required Time Crashed Time ES EF A1 2 0 2 A2 5 3 8 A3 5 3 8 11 A4 6 3 15 18 A5 4 18 22 A6 1 35 36 A7 6 4 36 40 A8 6 40 46 B1 3 0 3 B2 10 8 3 11 B3 10 11 21 B4 3 3 6 B5 4 3 8 11 B6 4 3 11 15 B7 7 0 7 B8 4 17 21 B9 8 22 30 B10 4 30 34 B11 5 30 35 B12 8 35 43 C1 5 3 8 C2 4 8 12 C3 1 8 9 C4 5 11 16 C5 6 11 17 13 7. 7 Figure 1 The network of activities It visualises the predecessor relationships, the early start and finish times (black) and the latest start and finish time (red). Nodes and bars in yard visualize the critical path.

No comments:

Post a Comment